Alexandra Theatre progresses with structural and roofing works
Construction at the Alexandra Theatre is making steady progress, with structural and roofing works moving forward as part of the wider Bognor Regis regeneration programme.
The site remains under the active management of Neilcott Construction Ltd, with safety and quality checks in place through regular project team inspections.
Recent progress highlights:
- concrete slab works underway: the reinforced concrete slab at first floor level is now being completed in two phases. The first section was successfully poured on 9 September, with the second section scheduled to be poured between 12 and 15 September, subject to weather and site conditions. This is a key structural milestone in shaping the new layout of the building
- shuttering and steel installation: steel reinforcement and shuttering (temporary moulds) were installed in preparation for the first-floor slab pour
- roof dormer works underway: work has begun on forming the dormers along the west side of the auditorium roof. These features are part of the building's heritage-sensitive reconfiguration and will support ventilation and natural light
Looking ahead:
- RC frame: construction of vertical columns and structural walls will progress from the new first-floor slab up to the underside of the roof
- ongoing roof works: the team will continue forming the dormers along the west-facing slope of the roof
- internal building works to progress: builders will begin works inside the existing building, including the main auditorium and newly created Studio 5 space
Commitment to delivery and safety
The project remains on track and continues to be delivered in line with the agreed construction programme. Health and safety standards remain a top priority, and the site continues to operate securely with minimal disruption to the surrounding area.
Further updates will be shared in our next scheduled release on 26 September.