Alexandra Theatre redevelopment continues to progress as site transitions to next key phase
The Alexandra Theatre redevelopment in Bognor Regis continues to move forward, with ground-level work making good progress and preparations underway for the next stage of construction. The project remains under the careful management of main contractor Neilcott Construction Ltd and is supported through regular site inspections by the project management team.
Recent progress highlights:
- pile testing underway: pile integrity testing is progressing across the site, with testing scheduled in phases as pile heads are exposed. These checks ensure that the new foundations meet all necessary structural standards
- reduced level dig in progress: work is continuing to carefully lower ground levels and expose pile heads in readiness for upcoming substructure works. This includes safe removal of material from the site as part of the transition to core construction
- scaffolding ready for reinstallation: scaffold materials have been delivered and are now stored inside the building. Internal scaffold construction will resume once finalised designs are approved, enabling essential roof work and further progress within the auditorium
- site remains secure and operational: pedestrian and vehicle access is being well managed, with a full-time gateman in place. Housekeeping on site remains good, with safety and cleanliness standards upheld
What's next:
- internal scaffolding installation: once design approval is confirmed, internal scaffolding will be installed to support work in the auditorium and roof areas. This will also enable safety netting and roof strip activities to commence
- drainage preparation to follow: as ground preparation concludes, below-ground drainage installation will begin, supporting the wider structural development of the building
Site hoardings update:
We're pleased to confirm that the first phase of infographic hoardings is now fully installed on site. These vibrant panels showcase key information about the Regis Rejuvenation programme, including timelines, project partners, and the design vision for the Alexandra Theatre and surrounding initiatives.
Looking ahead, the next section of hoardings will be installed on Tuesday 10 June. This will feature new wayfinding signage, helping to direct visitors and residents toward The Arcade and High Street. This signage also highlights the local businesses within The Arcade, encouraging footfall and visibility throughout the construction period.
Continued focus on safety and delivery
The redevelopment remains closely monitored through weekly site inspections and is progressing in line with the project plan. All site activity is supported by robust safety and quality control measures.
Cllr Roger Nash, Chair of the Economy Committee, said:
"It's fantastic to see the Alexandra Theatre project continuing to move forward. The newly installed hoardings are not only informative but also a great way of involving the community in the regeneration story. We're excited to see the next phase of signage going up to support our local businesses and improve wayfinding in the town centre."