Alexandra Theatre redevelopment continues with roof-level structural works

Poster by Arun District Council providing a project update on Alexandra Theatre construction work. It features two photos: one showing a wide view of the construction site with scaffolding under a clear blue sky, and another showing a closer view with workers and equipment. The title 'Project update' appears in an orange banner above 'Alexandra Theatre Construction Work' in bold blue text, with the council's logo on the rightThe next phase for the theatre in Bognor Regis will involve a reinforced concrete (RC) frame construction and roof-level structural works, critical in shaping the new spaces within the theatre and preparing the building for future fit-out and restoration.

The project is being delivered by Neilcott Construction Ltd on behalf of Arun District Council and remains under close supervision with regular site inspections.

Recent progress highlights:

  • RC frame rising on west elevation: work on the new RC frame to the building's west side has now progressed to just below the lower roof level, forming part of the permanent structural layout of the theatre's extension
  • first floor RC frame to north elevation: construction of the first-floor concrete frame on the northern side of the site is progressing well, supporting the continued build-up of the theatre's structure
  • dormer works ongoing: roof dormer construction to the west elevation of the existing auditorium continues, with the third dormer due for completion this week. These new dormers are a key part of restoring and reconfiguring the historic roof
  • internal works in progress: demolition and internal builders' works continue throughout the existing building, preparing spaces for refurbishment and modernisation

What's next:

  • continued structural progress: RC frame works will continue to rise, including the construction of vertical columns and internal walls
  • ongoing dormer construction: work on the dormers along the west-facing roof pitch will proceed, gradually completing each unit as part of the roof reconfiguration
  • internal layout development: builders' works will carry on inside the main auditorium and new Studio 5, shaping future performance and rehearsal spaces

Focused on safe delivery

As always, the site remains safe, secure and well-managed, with all works progressing in line with the agreed construction programme. The project team continues to coordinate carefully between trades to ensure delivery remains efficient and considerate of nearby public areas.

Stay informed

Regular updates will continue to be shared as the build moves forward. These updates form part of Arun District Council's wider communication programme for the Regis Rejuvenation initiative, ensuring residents, businesses and visitors remain informed throughout the regeneration process.

.