June 2022
There’s lots of work going on to progress the project and some temporary measures in place while we wait for materials to become available – a waiting game being faced by project managers up and down the country.
The shingle around the trees and the black base tarmac is due to be changed to coloured surfacing as part of the final design and the new planting and turf is being watered regularly during the warm weather and is already establishing
The difficulties being faced by the construction industry have delayed the delivery of some of the materials we requested but we will get there.
The main contractor is set to finish on site soon, at which point the water jets will be commissioned. To allow the space to be flexible for events all the pipes are already in place underground, so it’ll be all systems go once we get the green light. Watch this space!
April 2022
Read our latest press release: Place St Maur project in home stretch
February 2022
A water holding tank is being lifted into position at Place St Maur. This forms part of the circulation system for the water jets.
Work is now taking place at Place St Maur