Oldlands Farm

Full Planning application for the erection of a warehouse (Use Class B8) with ancillary office, associated vehicle parking, van storage, plant, ancillary structures, lighting landscaping and infrastructure works including earthworks to facilitate flood compensation area.

The Full Planning application has been approved under planning permission AL/87/21/PL

Latest news:

March 2023: 

  • commencement notice received

August 2022:

  • Construction Environment Management plan approved under AL/87/21/PL

August 2022:

Arboricultural Method Statement and Tree Protection Plan

An Arboricultural Method Statement (AMS) outlines the working methods for construction workers to adhere to during development. The Tree Protection Plan (TPP) forms part of the Arboricultural Method Statement and details the location of protection measures, such as the position of tree protection fencing. The following plans have been submitted:

  • Arboricultural Method Statement (Delta Simons) (September 2021)

Construction Management Plan

A construction management plan is a document that includes detailed information designed to minimise potential construction impacts on the environment considering logistics, traffic management and other impacts. The following plans have been submitted:

  • Construction Environmental Management Plan (November 2021) (ISG)

Useful information

Permitted hours

During the construction phase, no machinery/vehicles or plant shall be operated on the site, no process shall be carried out and no deliveries taken at or dispatched except between the hours of:

  • 8am and 6pm on Mondays to Fridays inclusive
  • 8am and 1pm on Saturdays
  • not at any time on Sundays or Public Holidays

Archive news

Previous planning application news for this site is as follows:

July 2021:

  • application AL/87/21/PL has been received at Oldlands Farm, Newlands Road for the Erection of a warehouse (Use Class B8) with an ancillary office, associated vehicle parking, van storage, plant, ancillary structures, lighting landscaping and infrastructure works including earthworks to facilitate flood compensation area. This site may affect listed buildings, may affect the character & appearance of the Shripney Conservation Area, is a Departure from the Development Plan, affects a Right of way & is in CIL Zone SP3 (Zero Rated) as other development.

Masterplan

Oldlands Farm site layout 

Please click on the image below to enlarge.

Oldlands Farm strategic site layout map

Alternative text: a map of the Oldlands Farm Newlands Road development site. This shows the proposed layout of commercial units and landscaping.

Please note the masterplan above is for illustrative purposes only and details are subject to change.

IFS

The Infrastructure Funding Statement (IFS) provides an update on all matters regarding developer contributions Section 106 (S.106) and Community Infrastructure Levy (CIL) during the previous financial year.

Our first IFS was published in September 2020 to cover the period from April 2019 to 31 March 2020. Please see our current IFS statement.

We collect all CIL contributions for all types of Infrastructure (from 1 April 2020) but we do not collect S.106 contributions for the provision of schools, highways, libraries or the fire service (although, in some cases, S.106 for these items are retained for these projects, in agreement with the county council). In most cases, these items are the responsibility of West Sussex County Council (WSCC). Therefore our IFS should be read in conjunction with the WSCC IFS to identify how S.106 from specific development sites has been spent across the board.   

If you wish to contact us regarding any of the strategic sites, please